Castlegar awards $6.7-million contract to bring idle sewage line back

Half of the south sewage plant has sat unused since a 2016 retrofit stalled. The full project now costs about $7.7 million.

Castlegar /
By The West Kootenay Current newsroom
A bridge over the Columbia River at Castlegar
Photo: waferboard via Wikimedia Commons, CC BY 2.0. A bridge over the Columbia River at Castlegar.

Castlegar council has approved a $6,731,928 contract with Chandos Construction to rebuild the north treatment train at the south sewage treatment plant.

The plant was built about 50 years ago with one treatment line. A second line was added between 2004 and 2006 so the plant could keep running if one side failed.

A 2016 retrofit added nitrogen removal to the newer line. Work on the older north line was put off for budget reasons, and it has been out of service since.

City engineering manager Ryan Niddery told council that growth, tougher environmental rules and the city's operating permit all point to bringing the north line back. Having two working lines gives the plant a backup.

The total project cost is now about $7.74 million. That is about $869,000 more than the budget council approved earlier this year. Council also gave readings to a temporary borrowing bylaw for the project.

Chandos was already working on the project as construction manager. Council's vote turns that agreement into a fixed-price contract.